NEWS · COMPANIES · #3049
AI data centers turn to converted jet engines to get power faster
Facing multi-year waits for grid connections and new turbines, some AI data centers are installing converted jet engines rebuilt to burn natural gas so they can come online faster. Companies named in reports include xAI (eight units in Mississippi for its Colossus 2 site), OpenAI (gas turbines at its Abilene Stargate site), and Crusoe (ordered converted units); the approach is faster but less efficient and more polluting than conventional gas plants.
KEY POINTS
- Facing multi-year waits for grid connections and new turbines, some AI data centers are installing converted jet engines rebuilt to burn natural gas so they can come online faster.
- Companies named in reports include xAI (eight units in Mississippi for its Colossus 2 site), OpenAI (gas turbines at its Abilene Stargate site), and Crusoe (ordered converted units); the approach is faster but less efficient and more polluting than conventional gas plants.
- This shows power supply is a material bottleneck for AI expansion, prompting stopgap on‑site generation with tradeoffs for efficiency and emissions.
WHY IT MATTERS
This shows power supply is a material bottleneck for AI expansion, prompting stopgap on‑site generation with tradeoffs for efficiency and emissions.